    S. No. Description Client Cost Rupees (Million)
    Power Plants
    1 150 M.W. Kabirwala Power Project near Multan.
    M/s CMIC (China) / Zurn-Nepco (USA)
    151.33
    2 3x210MW Oil Fired Thermal Power Project Unit 2, 3 & 4 at Jamshoro.

    M/s CMEC, China/ WAPDA
    131.42
    3 2 X 210 M.W Combined Cycle Power Project units 11 & 12, Kot Addu.
    M/s GEC Alsthom  of France/ WAPDA.
    232.80
    4 47 M.W Combined Cycle Power Project at Faisalabad.
    M/s HPEC, China/WAPDA
    121.45
    Industrial Plants
    1 8400 TPD, Lucky Cement Plant (Line-F), Silos, Internal Approach Roads, Mining Workshops & Triple Storey Hostel at Super Highway, Karachi.
    Lucky Cement Limited
    1000.000
    2 Pakland Cement Factory Extension Line – 2 at Dhabeji, Karachi Phase I & II M/s Pakland Cement Ltd. 159.85
    Highways, Bridges & Flyovers
    1

    Construction for Extension of Super Highway to Motorway (M-9) Project

    1) 2x Bridge No.7 and 8 at RD 75+750, 78+898

    1x Interchange at RD 80+851

    2) 2x Bridge No.9 and 10 at RD 90+065, 97+595

    1x Interchange at RD 98+601


    National Highway Authority
    786.206
    2 Periodic Maintenance Work on N-5 (Khanewal) Punjab – South Region
    National Highway Authority
    507.458
    3 Construction of 2-Lane Bridge Across River Indus at Khushalgarh, Dist Kohat & its Approach Roads Package-I. (Main Balanced Cantilever bridge and Road Work N-80)
    National Highway Authority
    1125.842
    4 Dualization of Sakrand Shaheed Benazirabad Road (Package –II) Km 7.500 to Km 18.95
    National Highway Authority
    597.293
    5 Const. of Bridge Over River Indus at Thakot.
    (Segmental Cantilever Bridge)

    National Highway Authority
    488.000
    6 Re-Construction of Collapsed Segment of Sher Shah Bridge on Karachi Northern Bypass (KNBP) at Karachi.
    National Highway Authority
    433.686
    7 Construction of Flyover along Kh-e-Hafiz at Gizri Commercial Area
    Pakistan Defence Officers Housing Authority
    560.829
    8 Construction of 3 Tier Flyover “KPT Interchange” at Hino Chowk Korangi Road Karachi including KPT Flyover at M.T. Khan Road.
    Karachi Port Trust
    1,000.000
    9 * Construction of Islamabad – Peshawar Motorway (M-1).
    National Highway Authority
    11,875.980
    10 Construction of Bridge and Road between Km 44+000 to 47+000 near Burida Camp, National Highway N-25
    M/s National Highway Authority
    81.23
    11 Construction of Railway Overhead Bridge at Ghaggar Phattak on National Highway from Karachi to Thatta including its Approach Roads.
    M/s National Highway Authority
    102.45
    12 Construction of Rotary Bridges No. 2 & 3, at Burhan Interchange, Islamabad – Peshawar Motorway.
    M/s Bayindir Insaat, Turkey
    231.00
    13 Rashid Minhas Road Flyover & Allied Works, at Karachi.
    M/s KDA & Railcop
    356.53
    Building Projects
    1 Construction of Maintenance Workshop at MKK Base Camp, Naimat, Tando Adam.
    United Energy Pakistan Limited
    33.585
    2 Construction of Office Building of Ministry of Science & Technology at Constitution Avenue, Islamabad.
    Ministry of Science & Technology
    634.572
    3 ** Package-I  Civil / Electrical / Plumbing Works & Local Area Networking) for Regional Taxpayers Office Karachi.
    Central Board of Revenue
    170.602
    4 Administration & Control Building for Kot Addu Thermal Power Plant. Centrally air-conditioned building with built-up area 9,500 sqm. (Kot Addu Combined Cycle Power Plant Unit 11 & 12, Each 210MW).
    M/s GEC Alsthom  of France/ WAPDA.
    232.80
    Ports & Harbours
    1 *** Reconstruction of Berths # 10 to 14 at East Wharves, Karachi for Karachi Port Trust.
    Karachi Port Trust
    5,515.426
    2 (a) Integrated Liquid Chemical Terminal & Storage Farm (Civil Work on shore) at Bin Qasim, Karachi
    M/s Preussag Noell (Germany) / Engro Pak Tank Terminal Ltd.
    156.57
    (b) Main office and Control building (centrally air-conditioned building built up area 3,500 sqm)
    3 LPG Storage and Bottling facility at Port Qasim SITE (Phase I).
    M/s Progas Pakistan (Pvt) Limited
    31.971